Redwood Road Construction Updates

Post Date:08/09/2017 3:18 PM
 

Redwood Road Madimimi Banner-01

Update - Nov. 3, 2017

 

IMG 2381

Mast arm and lanterns for Grandview Blvd. traffic signal

 

WIDENING: 400 South to Lake View Terrace Road

 

Redwood Road: Next week, crews will raise utility manholes and pour concrete collars. Steel plates will be placed over the manholes to allow the concrete time to cure. Drivers should use caution and slow down while driving over the steel plates. Mid-November, traffic is expected to shift to the west side of the road so crews can begin work on the east side.

Crews are reconstructing the multiuse trail on the east side of Redwood Road from Grandview Boulevard to Centennial Boulevard. This section of trail will be closed to pedestrian and recreational traffic for up to 30 days.

 

IMG 2383 - Compactor edited

Compacting road base materials near Grandview Blvd.

Grandview Boulevard and Lake View Terrace Road:
Crews are paving the outer lanes and expect to wrap up this weekend. Signal work is ongoing at Grandview Boulevard.

 

IMG 2358 - edited

Asphalt paver - north of Lake View Terrace Rd.

 

RESURFACING: Village Parkway south, approximately 10 miles

Next week, guardrail installation will continue on a section of Redwood Road approximately four miles south of Harbor Parkway. Intermittent lane closures will be in place to allow room for work. One-way flagging will be used to move traffic.

If you have any questions, contact a project representative at 801-997-5682 or redwoodsaratoga@utah.gov.

 

***

 

WIDENING

Upcoming Work:

▪Raising utility manholes
▪Temporary striping
▪Roadway reconstruction and utility work (east side of Redwood Road)
▪Utility work (at 400 South)

Raising utility manholes

 

Temporary striping

 

Roadway reconstruction and utility work (east side of Redwood Road)

 

Utility work (at 400 South)

Ongoing Work:

▪Asphalt paving
▪Utility work
▪Landscaping
▪Traffic signal installation (Grandview Boulevard)
▪Trail reconstruction (Grandview Boulevard to Centennial Boulevard)
▪Asphalt paving and utility work (Grandview Boulevard and Lake View Terrace Road)

Asphalt paving

 

Utility work

 

Landscaping

 

Traffic signal installation (Grandview Boulevard)

 

Trail reconstruction (Grandview Boulevard to Centennial Boulevard)

 

Asphalt paving and utility work (Grandview Boulevard and Lake View Terrace Road)

 

RESURFACING

Ongoing Work:

▪Guardrail installation
▪Project area cleanup

Guardrail installation

 

Project area cleanup

 

IMG 2382 - Landscaping

Landscaping work next to Redwood Rd.

 

What to Expect During Construction

▪Noise
▪Dust
▪Vibration
▪One-way flagging
▪Uneven lanes
▪Traffic delays
▪Lane shifts
▪Steel plates on roadway
▪Trucks entering/exiting work zone

Noise

 

Dust

 

Vibration

 

One-way flagging

 

Uneven lanes

 

Traffic delays

 

Lane shifts

 

Steel plates on roadway

 

Trucks entering/exiting work zone

 

Hours of Operation

Daytime Hours
Monday to Saturday (Sundays as needed)
6 a.m. to 7 p.m.

Nighttime Hours
Sunday to Friday (Saturdays as needed)
6 p.m. to 7 a.m.

Construction activities and schedule are weather- and equipment-dependent and subject to change.

 

***

 

Overview

The Utah Department of Transportation (UDOT) is improving Redwood Road south of Pioneer Crossing in Saratoga Springs over the next two years. The improvements, which began summer 2017, are designed to reduce congestion and extend the life of the roadway.

2017 Improvements

▪Road widening from three to five lanes (400 South to Lake View Terrace Road)
▪Dual left-turn lanes at Grandview Boulevard
▪Road resurfa

 