Delays on Redwood Road

Post Date:11/17/2017 5:34 PM

 

Redwood Road Madimimi Banner-01

Update - Dec. 14, 2017

 

Major Traffic Changes Coming to Redwood Road

Changes to traffic are coming to Redwood Road over the next week as crews work to stripe the five-lane configuration. Completion of the new travel lanes is expected to relieve traffic congestion in the area. The following depicts the upcoming work and traffic changes.

TOMORROW

Beginning Friday morning, Dec. 15, crews will stripe the new pavement on the east side of Redwood Road. One-way flagging will be used at intersections to complete this work.

At approximately 10 p.m., Redwood Road traffic will shift to the east side of the road from 400 South to Lake View Terrace Road. This traffic pattern will remain in place until next week. Drivers should pay attention, adhere to the construction signage and follow barrels.

NEXT WEEK

Beginning Tuesday, Dec. 19, crews will restripe the west side of Redwood Road and Grandview Boulevard. Restriping activities may last up to four days. One-way flagging will be used at intersections to complete this work.

Once striping is complete, all five lanes on Redwood Road from 400 South to Lake View Terrace Road and dual left-turn lanes on Grandview Boulevard will be open to the public. The new traffic pattern is expected to be in place by Friday, Dec. 22.

Construction activities and schedule are weather-dependent and subject to change.

 

IMG 2728 - Concrete blanket

Concrete blankets help cure concrete in colder temperatures

 

IMG 2716

Street light foundation

 

IMG 2715

Pedestrian signal foundation

 

WIDENING: 400 South to Lake View Terrace Road

Upcoming Work:

▪Pavement restriping on Redwood Road and Grandview Boulevard

Pavement restriping on Redwood Road and Grandview Boulevard

Ongoing Work:

▪Raising manholes
▪Utility work
▪Drainage work
▪Retaining wall installation (Grandview Boulevard)
▪Traffic signal installation (Grandview Boulevard)
▪Trail reconstruction (Grandview Boulevard to Centennial Boulevard)

Raising manholes

 

Utility work

 

Drainage work

 

Retaining wall installation (Grandview Boulevard)

 

Traffic signal installation (Grandview Boulevard)

 

Trail reconstruction (Grandview Boulevard to Centennial Boulevard)

 

IMG 2699 - Grandview

Grandview Boulevard

 

What to Expect During Construction

▪Noise
▪Dust
▪Vibration
▪One-way flagging
▪Uneven lanes
▪Traffic delays
▪Lane shifts
▪Steel plates on roadway
▪Trucks entering/exiting work zone

Noise

 

Dust

 

Vibration

 

One-way flagging

 

Uneven lanes

 

Traffic delays

 

Lane shifts

 

Steel plates on roadway

 

Trucks entering/exiting work zone

 

Hours of Operation

Daytime Hours
Monday through Saturday (Sundays as needed)
6 a.m. to 7 p.m.

Nighttime Hours
Sunday through Friday (Saturdays as needed)
6 p.m. to 7 a.m.

 

IMG 2731 - Drainage Work

Drainage work - east side of Redwood Road

 

Overview

The Utah Department of Transportation (UDOT) is improving Redwood Road south of Pioneer Crossing in Saratoga Springs over the next two years. The improvements, which began summer 2017, are designed to reduce congestion and extend the life of the roadway.

2017 Improvements

▪Road widening from three to five lanes (400 South to Lake View Terrace Road)
▪Dual left-turn lanes at Grandview Boulevard
▪Road resurfacing from Village Parkway south, approximately 10 miles
▪Extend bike lanes (400 South to Lake View Terrace Road)

Road widening from three to five lanes (400 South to Lake View Terrace Road)

 

Dual left-turn lanes at Grandview Boulevard

 

Road resurfacing from Village Parkway south, approximately 10 miles

 

Extend bike lanes (400 South to Lake View Terrace Road)

2018 Improvements

▪New east-west Continuous Flow Intersection (CFI) at Pioneer Crossing
▪Road widening from three to five lanes (Lake View Terrace Road to Village Parkway)
▪New traffic signals at Ring Road and Stillwater Drive
▪New trail from Pioneer Crossing to 400 South
▪New bike signal at Pony Express Parkway
▪Extend bike lanes (Lake View Terrace Road to Village Parkway)

New east-west Continuous Flow Intersection (CFI) at Pioneer Crossing

 

Road widening from three to five lanes (Lake View Terrace Road to Village Parkway)

 

New traffic signals at Ring Road and Stillwater Drive

 